§ 160-13. Procedure for tentative sketch plan.  


Latest version.
  • The procedure for the tentative sketch plan is as follows:
    A. 
    Applicant prepares sketch plan and application.
    B. 
    Applicant submits 12 copies of both the sketch plan and the application to the Township Manager.
    C. 
    Township Manager checks submission against checklist for completeness, and if:
    (1) 
    Submission is incomplete, immediately returns submission to applicant and indicates the deficiencies.
    (2) 
    Submission is complete, accepts sketch plan and application.
    D. 
    Township Manager shall distribute copies of the sketch plan and application to:
    (1) 
    Township Planning Commission: seven copies.
    (2) 
    Bucks County Planning Commission: two copies.
    (3) 
    Three copies shall be retained for the township files.
    E. 
    Bucks County Planning Commission reviews sketch plan and prepares analysis for review by the Upper Southampton Township Planning Commission.
    F. 
    At a regular meeting held following receipt of the complete submission to the Township Manager, and receipt of the review by the Bucks County Planning Commission, the Upper Southampton Township Planning Commission shall:
    [Amended 2-21-2006 by Ord. No. 375]
    (1) 
    Review the applicant's submission and the Bucks County Planning Commission's report.
    (2) 
    Advise applicant of its findings and of any issues of concern.
Amended 1-21-1992 by Ord. No. 295